Work in Progress This Week and Next Week:

Drop 2-1

  • Floor coating removal
  • Ceiling coating removal
  • Concrete Demo

Drop 2-6

  • Stucco plaster installation
  • Coating removal on the ceilings and floors
  • Concrete restoration

Drop 2-7

  • Metal lath installation
  • Stucco plaster installation
  • Concrete restoration

Drop 2-8

  • Stucco plaster installation
  • Concrete restoration
  • Framing installation (8th floor)
  • Sheathing installation (8th floor)

Drop 39 (Stair Tower 2)

  • Stucco coating application

Drop 4-3

  • Concrete restoration
  • Stucco plaster installation

Drop 4-4 (West)

  • Concrete restoration
  • Stucco plaster installation

Drop 4-4 (North)

  • Concrete restoration

Drop 9 (Stair Tower 3)

  • Stucco demo
  • Metal lath installation

Building 4 Walkways

  • Floor coating removal

Important Information/ Upcoming Milestones:

  • Building 2 Balconies
    • 2-1 (East and South) BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 2-6 (East) BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 2-7 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 2-8 (East) BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
  • Building 4 Balconies
    • 4-3 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 4-4 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
  • Building 4 Walkways
    • Floor 8 – Floor Closed – Oct. 11 – Nov. 8
    • Floor 7 – Floor Closed – Oct. 18 – Nov. 15
    • Floor 6 – Floor Closed – Oct. 25 – Nov. 22
    • Floor 5 – Floor Closed – Nov. 1 – Nov. 29
    • Floor 4 – Floor Closed – Nov. 8 – Dec. 6
    • Floor 3 – Floor Closed – Nov. 15 – Dec. 13
    • Floor 2 – Floor Closed – Nov. 22 – Dec. 20
    • Floor 1 – Floor Closed – Nov. 29 – Dec. 27

10-11-21

Work in Progress This Week and Next Week:

Drop 2-1

  • Floor coating removal
  • Ceiling coating removal

Drop 2-6

  • Insulation and sheathing installation

Drop 2-7

  • Framing installation
  • Insulation and sheathing installation
  • Concrete repair demo

Drop 2-8

  • Insulation and sheathing installation
  • Concrete repair demo

Drop 39 (Stair Tower 2)

  • Lath installation
  • Stucco installation

Drop 4-3

  • Insulation and sheathing installation
  • Metal lath installation

Drop 4-4

  • Insulation and sheathing installation
  • Metal lath installation

Drop 52b

  • Concrete repair demo

Drop 9

  • Mobilization

Important Information/ Upcoming Milestones:

  • Building 2 Balconies
    • 2-1 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 2-6 (EAST) BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 2-7 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 2-8 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
  • Building 4 Balconies
    • 4-3 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 4-4 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
  • Building 4 Walkways
    • Floor 8 – Floor Closed – Oct. 11 – Nov. 8
    • Floor 7 – Floor Closed – Oct. 18 – Nov. 15
    • Floor 6 – Floor Closed – Oct. 25 – Nov. 22
    • Floor 5 – Floor Closed – Nov. 1 – Nov. 29
    • Floor 4 – Floor Closed – Nov. 8 – Dec. 6
    • Floor 3 – Floor Closed – Nov. 15 – Dec. 13
    • Floor 2 – Floor Closed – Nov. 22 – Dec. 20
    • Floor 1 – Floor Closed – Nov. 29 – Dec. 27

09-24-21

Work in Progress This Week and Next Week:

Drop 2-1

  • Swing stage mobilization
  • Balcony protection installation

Drop 2-6

  • Stucco demolition
  • Framing repairs
  • Sheathing installation

Drop 2-7

  • Removal of existing ceiling and floor coatings
  • Stucco demolition
  • Framing repairs
  • Sheathing installation

Drop 2-8

  • Removal of existing ceiling and floor coatings
  • Stucco demolition
  • Framing repairs
  • Sheathing installation

Drop 35 (Stair Tower 2)

  • Mobilization
  • Stucco marking
  • Removal of existing floor coatings

Drop 39

  • Stucco demolition
  • Sheathing installation

Drop 4-3

  • Removal of existing ceiling and floor coatings
  • Stucco demolition
  • Framing repairs
  • Sheathing installation

Drop 4-4

  • Removal of existing ceiling and floor coatings
  • Stucco demolition
  • Framing repairs
  • Sheathing installation

Drop 52

  • Removal of existing ceiling and floor coatings

Important Information/ Upcoming Milestones:

  • Building 2 Balconies
    • 2-6 (EAST) BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 2-7 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 2-8 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
  • Building 4 Balconies
    • 4-3 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
    • 4-4 BALCONY STACK CLOSED (NO ACCESS TO ANY BALCONIES)
  • Building 4 Walkways
    • Floor 8 – Floor Closed – Oct. 11 – Nov. 8
    • Floor 7 – Floor Closed – Oct. 18 – Nov. 15
    • Floor 6 – Floor Closed – Oct. 25 – Nov. 22
    • Floor 5 – Floor Closed – Nov. 1 – Nov. 29
    • Floor 4 – Floor Closed – Nov. 8 – Dec. 6
    • Floor 3 – Floor Closed – Nov. 15 – Dec. 13
    • Floor 2 – Floor Closed – Nov. 22 – Dec. 20
    • Floor 1 – Floor Closed – Nov. 29 – Dec. 27